61850 Test Suite Pro can connect to multiple IEDs to facilitate substation level testing.

The process is exactly the same as connecting to a single IED.

1) Create or Open a Workspace

Creating a new workspace allows you to find IEDs by using an SCL file or using IP addresses

Opening an existing workspace will load a saved configuration to communicate with IEDs

2) Connect to IEDs in the Workspace

Connections are automatically created as data is needed from IEDs.

When you create a custom display with data objects from multiple IEDs, then 61850 Test Suite Pro will connect to each of those IEDs as needed to retrieve the data objects.

Example: data objects from three IEDs have been added to the custom display. The tool establishes a connection to all three IEDs and retrieves the data from reports because the data is available from a report and the data retrieval method is set to Reported.

 

You are here: Testing Substations > Finding Data in Substation > Connecting to Multiple IEDs
 
 

Support: +1 919.781.1931

support@trianglemicroworks.com

Submit a Support Request Online

Triangle MicroWorks, Inc.

© 2017 Triangle MicroWorks, Inc.All rights reserved.